As stated above, the Catalog of Investment Projects was developed as an annex to the Rivne SEAP. It contains data on 37 projects in the following municipal sectors:

1) heat supply;

2) water supply and sewage;

3) public transport;

4) outdoor lighting;

5) public buildings; and

6) residential buildings.

To assess investment attractiveness of the projects, different scenarios of price changes for energy and energy services were considered, also the required amounts of investments and economic performance indicators for each project proposal were indicated. For financing of the Sustainable Energy Action Plan of the city, it is proposed to involve several financial sources (funds of the international banking institutions, communal utilities, private investors, etc.). The Chart of distribution of financing by sectors is presented below. Total amount of investment projects financing for the period of 2015-2025 is over UAH 2.2 billion.

 Financing of Rivne SEAP Projects and Programs in 2015-2020 (UAH mln.)

 

HEAT SUPPLY

The total funding envisaged for 10 proposed projects is UAH 265.3 mln., average payback period – 3.7 years.

District heating services are provided in the city by two utilities: Rivneteploenergo LLC (98.6% of produced heat energy) and PJSC “ESCO-RIVNE” (1.4%). In total, the balance sheets of the heating utilitiesinclude: one heat power station (HPS), 40 boiler houses (19 of which are gas-fired and one operates on an alternative fuel – wood chips), 76 central heat substations (CHS), 48 IHSs (individual heat substations), one cogeneration unit in the boiler house, 203.2 km of heating networks (in double-pipe measurement). Total design capacity of boiler houses of these utilities is 753.4 Gcal/h, connected capacity – 311.1 Gcal/h. The following main problems in the sector include asignificant under-capacity of the district heating system (59%), which leads to increased heat energy losses in the networks; almost 75% of boiler house equipment has been in operation for more than 15 yearsit is physically and technologically outdated; the level of heating networks depreciation is over 70%; thelow level of the equipment of the buildings with IHSs and, accordingly, low quality of the services provided.

The Catalog of Investment Projects in this sector includes replacement and relaying of the heating networks with the use of 3,975 m of pre-insulated pipes in double-pipe measurement; comprehensive thermal modernization of the 40 Gcal/hcapacity boiler house at 225-K Soborna Street including the replacement of the pumping and purifying equipment; reconstruction of the boiler house at 75-B Kniazia Volodymyra Street including replacing equipment with energy efficient equipment; liquidation of two low-profit boiler houses and the switching of heat load to other boiler houses; replacement of the burners in 21 old boilers; modernization of the water chemical treatment systems in the boiler houses; replacement of water-to-water heaters with highly efficient baffle heaters; installation of solid fuel boiler and electric water heaters to improve the energy efficiency of the remote boiler houses; cleaning, flushing and the operational tuning of the boilers.

If all of the measures in the heat generation and transportation sector are implemented, it would reduce CO2 emissions by 32,917 t/year or 6.18% of the baseline. Energy resources consumption would fall by 16,459 th. m3 of natural gas and 3,658 MWh of electricity.

The city has established cooperation with EIB and expressed its intention to take part in the “Ukraine Municipal Infrastructure Development Program” project. Plans include implementing the “Modernization of Heat Supply Objects in Western Part of Rivne” investment project, which will implement a set of measures aimed at reducing heat energy losses in the mains of the municipal heating networks, as well as reduce heat energy consumption in residential buildings while reducing the communal bills of the populace.

 

WATER SUPPLY AND SEWAGE

The total funding envisaged for the six proposed projects is UAH 167.2 mln., average payback period – 3.8 years.

District water supply and sewage services are provided in the city by CU Rivneoblvodokanal which operates and services 118 artesian wells, four deferrization stations with 20 filters, seven water pumping stations, 21 sewage pumping station, 216.5 km of water pipes and 414.8 km of water distribution networks, 227.5 km of sewage networks. Water supply comes from underground sources (three water intakes)water is additionally purified at the deferrization station. Residents consumed 12,408.7 th. m3 of water in 2014 and sewage effluent of 18,970.1 th. m3. Sewage effluent is pumped to the municipal purification facilities as well as the purification facilities of Rivneazot company. Electricity consumption for water supply and sewage in 2014 was 29,789 MWh. In 2014. There were 653 water supply network emergencies andsewage network emergencies.

The Catalog of Investment Projects in this sector includesreplacing booster pumps at 19 water stations and two sewage stations with energy efficient pumps with frequency converters; reconstructing 3,773 mof emergency water networks with a further reduction of service pressure; reconstructing purification facilities and constructing a sewage effluent purification plant with the capacity 30 th. m3/day; installing an automated dispatch supervision and control system (ADSCS) for the water utility equipment.

If all measures in the water supply and sewage sector are implemented, it would reduce CO2 emissions by 5,763 t/year or 1.08% of the baseline. Total energy resources consumption would fall by 4,968 MWh of electricity a year.

On 16 June 2016, the deputies of the Rivne City Council supported the participation of the Rivne City Council Executive Committee in the “Ukraine Municipal Infrastructure Development Program” implemented with EIB 5.5 million loan for financing of subproject “Introduction of Energy Saving in Facilities and Buildings in Communal Ownership of Rivne” project. It provides for implementing measures to improve energy efficiency in 30-40 secondary schools, sports schools, music schools, medical institutions, and kindergartens in the city.

 

PUBLIC TRANSPORT

The total funding envisaged for the five proposed projects is UAH 358.8 mln., average payback period – 2 years.

Rivne has 300.5 km of automobile roads. There are eight automobile bridges and four crossovers in the city. Public passenger transportation in the city is performed by trolleybuses, buses and private buses (mostly small capacity passenger buses) operating as fixed-route taxies. Bus transportation is conducted by different kinds of business entities: 11 of these are private companies and 93 are private carriers. 35 bus routes are operated by five buses and 350 buses operating as fixed-route taxiesThe average operating life of the bus rolling stock is 13 years. There are 728.6 km of bus lines. Municipal passenger transportation services via electric transport are provided by CU Rivneelectroavtotrans. Up to 66 trolleybuses work on 10 routes. There are 60.8 km of trolleybus lines and 8 traction substations. The average age of the trolleybuses exceeds 26 years. The amount of electricity consumed by municipal transport in 2014 was 5,516 MWh, diesel fuel – 5,715 th.

Investment projects in this sector include:replacing 75 outdated trolleybuses, replacing the traction systems of 32 trolleybuses with the installation of impulse driving systems, equipping 55 trolleybuses with electricity meters, and switching 408 company and passenger small capacity buses to biodiesel fuel.

If all measures in the transport sector are implemented, it would reduce CO2 emissions by 8,951 t/year or 1.68% of the baseline. Total energy resources consumption would fall by 2,978 MWh of electricity a year.

 

OUTDOOR LIGHTING

The total funding envisaged for the proposed two projects is UAH 41.6 mln., average payback period – 8.5 years.

The outdoor lighting networks of the city are on the balance sheet of CU Misksvitlo. As of 2015, the utility operated 260.1 km of cable and air outdoor lighting networks, including 238.42 km of air lines and 21.68 km of cable networks. In 2010-2014, the number of lighting fixtures increased from 8,711 to 9,559 units (by 10%). The municipal lighting system uses over 30 types of light sources, but the most used are arc sodium tubing lamps (DNaT) which, despite their high energy efficiency, require frequent servicing and have a short lifecycle. The municipal outdoor lighting is controlled from the central dispatch point of the Kaskad automated system via control stations and cabinets. Misksvitlo has started implementing remote control for outdoor lighting through GSM-network radio channels, with computer data processing. To identify the amount of electricity consumed for the needs of outdoor lighting, 135 devices of metering differentiated by time are used. Most of the electricity is consumed during the night tariff time(on average, 90% of total consumption, which in 2014 was 3,436 MWh).

Investment projects in this sector include: introducing low energy lighting sources with energy efficient LED lamps – 8,255 units, repairing the overhead power transmission lines, and installing 20 autonomous street LED lighting units with solar batteries for the lighting of unsupervised pedestrian crossings.

If all measures in the outdoor lighting sector are implemented, it would reduce CO2 emissions by 1,497 t/year or 0.28% of the baseline. Total annual energy resources consumption would fall by 1,290 MWh of electricity a year.

 

PUBLIC BUILDINGS

The total funding envisaged for the four proposed projects is UAH 727.7 mln., average payback period – 7 years.

There are152 public buildings subordinated to the city (76 educational establishments, 8 health protection institutions, cultural and social protection institutions) with a total heated space of 381,8 m2. The most significant heat energy consumers are municipal educational establishments (71% of total consumption) and health protection institutions (17% of total consumption). The conditional heat energy consumption in the buildings is 175 kWh/m2 a year in average, which is significantly higher than the European norms (15-45 kWh/m2) and normative values (45-70 kWh/m2) according to DBN B.2.6-31:2006 “Heat Insulation of Buildings” with amendment # 1. Also, the norms on indoor microclimate are not observed in the premises, which affects the high energy consumption by the public buildings in the city. In 2014, the public buildings sector consumed the following amounts of energy resources: 223,600 mof natural gas, 30,787.3 Gcal of heat energy and 7,413 MWh of electricity.

Investment projects in this sector includecomprehensive thermal modernization of 84 educational establishments, health protection and cultural institutions (insulation of the building envelopes and roofs, replacing windows with energy efficient ones, modernizing entrance units, installing individual heat substations with the capacity for automated weather-based control, balancing of the heating systems, insulating indoor heating systems, renovating ventilation systems with the installation of recuperation units, replacing mixers in the water supply systems with energy efficient ones, installing aerators); replacing incandescent lamps with energy efficient LED lamps – 11,450 units; equipping 12 educational establishments with heat energy meters with the capacity for consumption control.

Implementing the project proposals in the sector of public buildings will reduce CO2 emissions into the atmosphere by 13,425 t/year or 2.52% of the baseline. Total energy resources consumption will fall by 5,436 m3 of natural gas and 1,145 MWh of electricity a year.

On 23 June 2016,the deputies of the Rivne City Council supported the decision to take out a NEFCO loan for financing the “Introduction of Energy Saving in Three Buildings and of Energy Management System in Public Buildings of Rivne”investment project. The loan amount is over UAH 8.2 million.

 

RESIDENTIAL BUILDINGS

The total funding envisaged for the proposed six projects in this sector is UAH 637.2 mln., average payback period – 5.8 years.

Residential housing stock of the city consists of 1,363 residential buildings. The total space of multi-apartment buildings is 4,638.4 th. m2, and 74% of buildings have six floors or less. The residential buildings are managed by five housing and communal companies of different ownership forms. Most of the buildings belong to the first mass construction series of the 1950-1960s. They are technologically obsolete, have a number of constructive deficiencies and do not comply with modern comfort norms. Energy consumption to ensure comfortable conditions in such buildings exceeds modern norms (15-45 kWh/m2 according to the European norms and 45-70 kWh/m2 according to DBN B.2.6-31:2006 “Heat Insulation of Buildings” with amendment # 1) by 2.5-3 times, and cause unreasonably high operating expenses for providing heating and water supply services. Only 8% of existing residential stock was constructed after 1991. There are 230 residential buildings equipped with heat energy meters. Per-resident space is 18 m2. In 2014, the residential buildings sector consumed the following amounts of energy resources: 51,247.2th. m3of natural gas, 414.9 Gcal of heat energy and 140.5 th. MWh of electricity.

Investment projects in the residential building sector includeclosing four central heat substations (CHSs) and installing 17 modular individual heat substations (IHSs); comprehensive thermal modernization of 20 multi-apartment residential building (insulating building envelopes, roofs and basements, replacing windows, balancing of the heating systems, installing individual heat substation and thermostatic control valves on the heating radiators, heat insulation of internal pipes); installing electricity meters in public areas of 87 buildings; capital renovation and insulation of building envelopes for 190 multi-apartment buildings; capital renovation and renovation of 449 elevators.

Implementing the project proposals in the residential building sector on the stage of heat consumption will decrease general CO2 emissions by 32,528 t/year or 6.16% of the baseline. Total annual energy resources consumption would fall by 8,549 th. m3 of natural gas and 1,665 MWh of electricity.

 

ALTERNATIVE ENERGY SOURCES

The total funding envisaged for the proposed 3 projects in this sector is UAH 13.9 mln., average payback period – 0.9 years.

As of 2015, the whole amount of solid waste created in the city is removed and utilized at the municipal landfill (in average – 1,080 th. m3a year). The average space of the landfill started in 1959 is 21.15 ha. Since 2013, the first in Ukraine waste incineration plant was functioning in the city, its capacity is 120,000 t/year. The company produces fuel from solid domestic waste according to the “fluff” technology (lax secondary fuel), which allowed the city to process up to 40% of municipal waste. The plant is not functioning now due to a lack of legislative regulation. Separate waste collection was introduced in the city.

The Catalog of Investment Projects in this sector includesconstructing a cogeneration plant for combined electricity and heat energy production with the utilization of landfill gas; creating an automobile gas filling compressor station on biogas as fuel for the trucks servicing the solid waste landfill; resumption of work of the waste incineration plant and production of secondary fuel.

Implementing the project proposals in the sector of alternative energy sources will reduce CO2 emissions into the atmosphere by 6,184 t/year or 1.16% of the baseline. Total energy resources consumption will fall by 861,000 m3 of natural gas and 3,908 MWh of electricity a year.