The USAID Project provides support to the city in the creation of the municipal energy management system and, in particular, Automated System for Remote Energy Monitoring (ASREM).

With ASREM, the processes of energy distribution monitoring, technical condition of infrastructure for energy supply, status of infrastructure use for fuel and energy balances formation, etc. will be subject to complete or partial automation.

The cost of implementing the comprehensive energy management system is about 50% of the estimated savings. The estimated savings of energy resources will be at least 10% of the annual consumption by the municipal public building sector .

It is planned to complete the introduction of the energy management system by the end of 2016. All measures will be financed from the municipal budget. Estimated project cost – UAH 6.9 million.